Published January 31, 2014

Construction crews are hard at work on numerous projects throughout the district. Below is a list of the county's current construction projects.

Brentwood High School Auditorium

The Williamson County Schools Facilities and Construction Department has advertised the project for competitive bids, however bidding of this project has been delayed by 14 days due to revisions to existing utilities. An addendum will be issued to all bidders. Construction will begin in March, weather permitting.

Brentwood Middle School - Phase 2

Phase 2 began during the recent winter break. The HVAC units in the gymnasium have been removed and replaced as well as the units that serve the cafeteria, kitchen and locker rooms. The remaining work will be done during Spring Break and over the summer.

Centennial Baseball Field Renovation

The project is currently under design, which should take about two weeks. After that, the Facilities and Construction Department will advertise it for a competitive bid. Construction will begin following baseball season.

Centennial High School Auditorium

Inclement weather has delayed construction by approximately 34 days. The building pad has been excavated and foundation preparation has started. Underground utilities, fire loop water and electrical primary have been installed, and foundation construction will resume once temperatures stabilize above 40 degrees.

Fairview Middle School Auditorium

Inclement weather has delayed construction by approximately 15 days. Demolition of existing utilities has started, the bus loop island has been removed and the parking lot lighting has been relocated.

New Nolensville Elementary/Middle School & High School Projects

The design teams for each school are moving forward with the goal of having each ready for bidding in early spring of 2014. All three schools are scheduled for completion in Fall 2016.

Woodland Middle School Auditorium

Crews are busy at the site of Woodland Middle School's new auditorium. The contractor has completed construction of the building pad, foundations, and underground utilities. Unit masonry walls are underway albeit progress has been slow due to inclement weather. The estimated date of completion for this project is early fall of 2014.