Aerial view taken on May 19
|
Allendale Elementary:
- Brick veneer is complete
- All casework is complete
- Gymnasium floor installation in progress
- Sidewalk is 70% complete
- Playground equipment is 20% complete
- Scheduled to open in August, 2010
|
Aerial view taken on June 7
|
Spring Station Middle:
- 95% of interior punch list complete
- Fire alarms tested with city and state
- Fencing completed on baseball field
- Sodding in progress around building
- Planting, seeding and paving in progress
- Scheduled to open in August, 2010
|
Aerial view taken on June 7
|
Summit High:
- Foundation block complete
- Geothermal laterals complete
- Site grading underway at parking lots
- Load bearing masonry in progress
- Structural steel in progress at entrance
- Scheduled to open in 2011
|
Aerial view taken on June 17
|
Pearre Creek Elementary:
- Sidewalks 60% complete
- Masonry complete
- Casework in progress
- Gymnasium bleachers complete
- Geothermal complete
- Scheduled to open in August, 2010
|