Aerial view taken on April 15
|
Allendale Elementary:
- Brick veneer 70% complete
- Storm drainage 90% complete
- Casework installation in progress
- Window glass installation in progress
- Fireproofing is complete
- Scheduled to open in August, 2010
|
Aerial view taken on May 19
|
Spring Station Middle:
- Completed wood flooring in gym
- Bleacher installation complete
- Locker installation in progress
- Started fencing at ball fields
- Exterior concrete 60% complete
- Scheduled to open in August, 2010
|
Aerial view taken on May 6
|
Summit High:
- Completed foundation block at G wing
- Geothermal drilling in progress
- Block wall construction underway
- Auxiliary gym walls 75% complete
- Retention pond complete
- Scheduled to open in 2011
|
Aerial view taken on May 19
|
Pearre Creek Elementary:
- Sidewalks 60% complete
- Masonry complete
- Casework in progress
- Gymnasium bleachers complete
- Geothermal complete
- Scheduled to open in August, 2010
|